Improvement
-
Resolution: Fixed
-
Minor
-
3.9.19, 3.11.12, 4.0.6, 4.1.1
-
MOODLE_311_STABLE, MOODLE_39_STABLE, MOODLE_400_STABLE, MOODLE_401_STABLE
-
MOODLE_402_STABLE
-
The current \enrol_lti\task\sync_grades scheduled task processes all LTI tools in series when it doesn't need to. Large Moodle sites functioning as an LTI Provider can run into bottlenecks with the process taking a long time.
To resolve this, I've created a new ad-hoc task that is spawned via the existing scheduled task. This allows multiple gradesyncs to run in parallel.
- has been marked as being related by
-
MDL-82321 Task lti advantage sync grades too verbose for high numbers of lti activities
-
- Open
-
- has to be done before
-
MDLQA-17900 CLONE - Grades can be returned to the remote platform after grading an activity shared using LTI
-
- Passed
-
-
MDLQA-18397 CLONE - Grades can be returned to the remote platform after grading an activity shared using LTI
-
- Passed
-
-
MDLQA-18882 CLONE - Grades can be returned to the remote platform after grading an activity shared using LTI
-
- Passed
-
-
MDLQA-19340 CLONE - Grades can be returned to the remote platform after grading an activity shared using LTI
-
- Passed
-
-
MDLQA-16119 Grades can be returned to the remote platform after grading an activity shared using LTI
-
- On Hold
-